Market Sector: Waterfront Structures
Technology: Fyfe Europe
Country: USA
Concrete Repair and Protection of Chula Vista Bayside Park Pier, California
Project: Concrete Repair and Protection on Chula Vista Bayside Park Pier
Location: Chula Vista, CA
Client: Port of San Diego
Contract Duration: 10 weeks
Scope of Works:
• Concrete Repair and Protection to the pier soffit and piles on the pier substructure
• Spot concrete repair of corroded handrails concrete curb on the pier substructure
• Repair and replacement of the wave attenuation panels
• Pier deck resurfacing
Project Description:
Fibrwrap Construction Inc. performed concrete repair and protection works on the pier substructure mainly with the implementation of Tyfo® Fibrwrap Systems.
Actually the engineer of record, Triton Engineers specified the Tyfo® SCH-41 Carbon Fiber with the use of the Tyfo® SW-1 epoxy, specially developed for underwater curing.
The full scope of the project was successfully completed in 10 weeks.
One year after the completion of works a warranty inspection from the client, the engineer of record and FCI Agency, was conducted and it was found that the performance of both structural and no-structural improvements remained in prime condition