Fibrwrap Construction Lebanon SARL

Fibrwrap Lebanon: Slab Strengthening for Service Penetrations of Premier Inn Hotel, Kingston Upon Thames, London, UK

Fibrwrap Construction

8690 Red Oak Street
Rancho Cucamonga" />
  • Slab Strengthening for Service Penetrations of Premier Inn Hotel, Kingston Upon Thames, London, UKContact Us
  • Tyfo® Product Catalog

    Fyfe Company is ISO-certified and the manufacturer of FRP products and strengthening systems.

    Fibrwrap Customer Survey

    We value your feedback.

    Tyfo® System Pipe Animation

    Fibrwrap Construction uses the Tyfo® FRP system to rehabilitate and strengthen pipelines.

    Fibrwrap Construction

    8690 Red Oak Street
    Rancho Cucamonga" />
  • Slab Strengthening for Service Penetrations of Premier Inn Hotel, Kingston Upon Thames, London, UKContact Us
  • Tyfo® Product Catalog

    Fyfe Company is ISO-certified and the manufacturer of FRP products and strengthening systems.

    Fibrwrap Customer Survey

    We value your feedback.

    Tyfo® System Pipe Animation

    Fibrwrap Construction uses the Tyfo® FRP system to rehabilitate and strengthen pipelines.

    Slab Strengthening for Service Penetrations of Premier Inn Hotel, Kingston Upon Thames, London, UK

    Project: Slab Strengthening for Service Penetrations of Premier Inn Hotel
    Location: Kingston Upon Thames, London, UK
    Client: Barnes Construction
    Contract Duration: 4 Weeks

    Scope of Works:
    • Slab strengthening for service penetrations using Tyfo SCH Carbon Fibre Systems

     

    Project Description:
    An office to hotel conversion in Kingston Upon Thames was the project for Barnes Construction from Suffolk. The original 1960’s concrete framed building in the town centre had quite restrictive head room between slabs. We were contacted by the clients consulting engineers to help with the transfer of loads through the slabs due to cutting of the reinforcement through drilling service holes. A very common case for us here at Fibrwrap UK, we designed a simple solution using Tyfo SCH Carbon Fibre Systems, we designed 3 or 4 details that could be repeated for each bedroom/bathroom configuration and also a particular design for the restaurant/kitchen ventilation. Below are some images of the Carbon Fibre Strengthening prior to the drilling taking place.
    Be aware that by carrying out the strengthening prior to the drilling taking place you eliminate the requirement for temporary works saving time and money. And because the Tyfo Fibrwrap systems is typically 1mm thick per layer there are no restrictions on head height.